Villa renovation in The Springs and The Meadows, one developer, one route.
In The Springs and The Meadows, work beyond internal finishes needs an Emaar NOC first, lodged on the Emirates Living portal, then a DDA Building Modification permit, and a completion inspection before the deposit is released. Both communities sit in Emaar’s Emirates Living, so one route covers a Springs townhouse and a seven-bedroom Meadows villa alike. Mignon draws, lodges and builds it under one contract.
Last reviewed 1 Nov 2026 Sources and dates

Priced per sqft of built-up area
-
ST
Travertine -
MB
Marble -
VN
Walnut -
MT
Brass
At a glance
The Springs and The Meadows, at a glance
- Master developer
- Emaar
- Master community
- Emirates Living, managed by Emaar Community Management
- NOC issued by
- Emaar, via the Alterations or Home Modifications tab
- Permit authority
- DDA · Building Modification: Design, Permit, Completion
- Where to apply
- emiratesliving.ae community portal; contractors at ecmpermits.ae
- The Springs
- 4,856 homes in 14 sub-communities; townhouses, Types 1 to 4, end or middle
- The Meadows
- Nine sub-communities of two-storey detached villas, 3 to 7 bedrooms
- Handover era
- Mid-2000s
Approvals · Emirates Living
The Springs and Meadows route, in six steps
Every alteration in Emirates Living goes to Emaar first. DDA then approves the design, issues the permit and closes the job. The steps are the same for a Springs townhouse and a Meadows villa.
Step 01 / 06
MIGNONName the type, then the scope
- Done by
- Mignon, at the site survey
- Where
- Your villa
- You receive
- Villa type confirmed, as-built drawings, the scope
What to know
A Type 3M and a 3E share a bedroom count but not a plot or a party wall. We record the type and any earlier changes, because Emaar reviews the house as it stands.
Step 02 / 06
EMAAREmaar NOC
- Issued by
- Emaar
- Where
- emiratesliving.ae → Alterations or Home Modifications
- You receive
- The Emaar NOC, once the approval fee is paid
What to know
ECM’s Emirates Living FAQ is plain: any alteration to the villa has to be approved by Emaar, carports, garden pergolas and pool renovations included.
Step 03 / 06
DDADDA Building Modification, Design
- Issued by
- DDA; the consultant applies
- Where
- DDA Zoning e-Services
- You receive
- Stamped, approved drawings
What to know
Needed where the scope changes layout, structure or services. A Civil Defence NOC joins the file where fire and life-safety systems change.
Step 04 / 06
DDADDA Building Modification, Permit
- Issued by
- DDA; the contractor applies
- Where
- DDA Zoning e-Services
- You receive
- The building modification permit
What to know
Charged per square foot of added or relevant built-up area, with the appointment letter signed by owner, consultant and contractor.
Step 05 / 06
ECMECM contractor entry permit
- Issued by
- Emaar Community Management
- Where
- ecmpermits.ae
- You receive
- An entry permit for Emirates Living and this contract
What to know
Issued per community and per contract. Emaar’s factsheet places it after the NOC and the authority approvals.
Step 06 / 06
EMAAR + DDACompletion, then the deposit
- Issued by
- Emaar, then DDA
- Where
- emiratesliving.ae; DDA Completion
- You receive
- Emaar’s inspection approval, the DDA completion certificate, the deposit back
What to know
Book the inspection on the portal, then claim the deposit within two years of paying it. DDA needs a Civil Defence completion certificate where fire and life-safety systems changed.
Read the detail Close the detail
Emirates Living is one master community for The Springs, The Meadows, The Lakes, Emirates Hills and Hattan. The Springs and The Meadows share the portal, the rulebook and the route, which is why this page covers both.
Most Springs scopes are internal, and still need the NOC. The DDA steps apply once the drawings move walls, add area or change services.
Documents
What goes into an Emirates Living submission
Emaar’s checklist covers the NOC, DDA adds its own for design, permit and completion. One survey feeds both.
Concept visualisationYou provide
- Title deed and owner ID
- Photos of the areas to change
- Earlier NOCs, if a previous owner extended or altered the villa
We prepare
- A detailed scope of works
- Proposed plans, elevations and sections
- 3D visualisations where they help
- Structural calculations for any opened wall
- Owner, consultant and contractor appointment letter
Registered with Emaar & DDA
- Contractor or consultant trade licence, registered in Dubai
- DDA site plan or DLD plot plan where needed
- Entry-permit registration on ecmpermits.ae
Read the detail Close the detail
Many Springs villas have changed hands more than once. A carport or rear room built without an NOC is found at inspection, so we note what we find on the survey and raise it with Emaar first.
Fees & timelines
Published fees and timelines in Emirates Living.
The figures below are Emaar’s and DDA’s own, each dated. They change over time, so we confirm every one at application.
The villa programmeAround 12 months, brief to handover
| Item | Figure | Timing | Charged by | Notes |
|---|---|---|---|---|
| Emaar NOC, review fee | AED 500 | Paid on application | Emaar | Non-refundable. Confirm at application. |
| Emaar NOC, approval fee | AED 1,000 / 2,000 | 3 business days | Emaar | AED 1,000 minor works, AED 2,000 major works; the review fee is deducted. Confirm at application. |
| Landscaping, paving or external paint NOC | AED 100 | 2 business days | Emaar | Confirm at application. |
| Security deposit | AED 5,000 | Refunded after completion | Emaar | Refundable, claimed within two years of payment. Confirm at application. |
| Added GFA or BUA on an extension | Charged, rate not published | Quoted with the application | Emaar | Emaar confirms the rate in writing. Confirm at application. |
| DDA Building Modification, Design | AED 1,500 + fees | 5 working days; valid 6 months | DDA | Plus AED 10 Knowledge and AED 10 Innovation Dirham. Confirm at application. |
| DDA Building Modification, Permit | AED 1 / sq ft + AED 20 | 2 working days | DDA | Per sq ft of added or relevant BUA; renewal AED 200 per 3 months, up to a year. Confirm at application. |
| DDA Building Modification, Completion | No fee, standard | 3 working days | DDA | Standard submission. Confirm at application. |
Read the detail Close the detail
Figures reflect Emaar and DDA published procedures and should be confirmed at application.
Emaar publishes the fees above and says added GFA or BUA is charged, without the rate, so we ask for it in writing with the application. The deposit amount is from Emaar’s factsheet; DDA’s pages are undated, so they show the month we read them.
What's allowed
What a Springs or Meadows owner can change.
ECM’s Emirates Living FAQ and the villa rulebook split every job three ways. We confirm each item for your specific villa at the survey.
Allowed without an NOC 4
- Internal painting
- Furniture
- Electrical fixtures
- Regular maintenance
Needs approval first 9
- Carport extensions
- Garden pergolas
- Pool renovations
- Any villa alteration, inside or out
- AC replacement, never on the facade
- Awnings and shade matching the villa’s paint or woodwork
- Removing a tree
- Significant window or ceiling changes
- Extensions, townhouses included, case by case
Not allowed 5
- Changes to the villa exterior
- Balcony enclosures in townhouses
- Visible solar panels
- Lights on boundary walls or the villa exterior
- Wells and reverse-osmosis plants
Read the detail Close the detail
Emaar approves extensions on application, townhouses included, and each case is reviewed on its drawings, often with a cap on the added area relative to the existing BUA. Exterior changes are not permitted, so a Springs villa keeps its original colour, while the garden, shade and pool can still change with an NOC.
Rules on site
Rules on site in Emirates Living.
The Emirates Living villa rulebook sets these hours for The Springs and The Meadows alike: construction 10:00 to 13:00 and 15:00 to 17:00, Monday to Saturday.
The working day Emirates Living villa rulebook
- Monworks
- Tueworks
- Wedworks
- Thuworks
- Friworks
- Satworks
- Sunno works
-
Entry permits
Only contractors with an approved ECM entry permit get in; the owner answers for their conduct.
-
Deliveries
48 hours’ notice; bulk deliveries Monday to Saturday, 10:00 to 13:00.
-
Noise
Excessive if a neighbour hears it with windows and doors shut, which matters on a shared party wall.
-
Debris
Removed at the resident’s expense; packing cleared the same day.
-
AC units
Never on the facade or visible from common areas or a neighbouring villa.
-
Penalties
A notice of violation, then fines on the service-fee account.
Read the detail Close the detail
The contractor portal gives 08:00 to 17:30 with Fridays off. The newer rulebook names Sundays as the rest day, so our programme follows it and we confirm with the community office at mobilisation.
The Meadows
The Meadows: detached villas on the same route.
The Meadows is nine sub-communities of two-storey detached villas with 3 to 7 bedrooms, around lakes and the Montgomerie course. The Emaar NOC and DDA route is identical to The Springs.
Detached, two storeys
3–4 bedroom villas
- Bedrooms
- 3–4 bed
Typical renovation Kitchen and family room joined; bathrooms and AC renewed.
Detached, two storeys
5 bedroom villas
- Bedrooms
- 5 bed
Typical renovation Full remodel with a rewire and replumb; majlis or study added inside the footprint.
Detached, larger plots
6–7 bedroom villas
- Bedrooms
- 6–7 bed
Typical renovation Phased whole-house work; pool and garden redrawn with the house.
Meadows 1 and others
Lake and golf edges
- Bedrooms
- 3–7 bed
Typical renovation Rooms replanned toward the view; the glazing stays as built.
Read the detail Close the detail
No reliable public list of Meadows villa types exists, so we group them by size. A Meadows extension goes to Emaar on application, as anywhere in Emirates Living, then carries Emaar’s area charge and the DDA permit.
Common projects
What Springs and Meadows villas usually need.
Twenty-year-old houses on tight plots: services, kitchens and the ground floor plan, more than finishes alone.
Kitchens opened up
The most common request. It moves a wall, so it is an Emaar alteration with DDA drawings.
Services at twenty years
AC, water heaters, pumps and drainage from the first build are at end of life; renewed with ceilings open.
Bathrooms, stripped back
Stripped to the screed; waterproofing renewed before new stone goes down.
Carport paving that has sunk
Sunken interlock is often caused by leaks, and is the owner’s repair. We trace the leak first.
Middle units: the party walls
Neighbours on both sides: demolition in the morning window, structure kept inside your own walls.
Design renders
Rooms agreed as renders while Emaar reviews the plan.
Design renders, not photographs of a villa in The Springs or The Meadows: rooms agreed while Emaar reviews the plan.
-
Render Media wall with a linear fire and walnut shelving. -
Render Double-height dining under a sculptural chandelier. -
Render Living room, curved sofa and stair. -
Render Living room, with the dining table and kitchen beyond.
Renders and samples, not photographs. Tap a tab to filter the set.
See our completed villa projects →Springs & Meadows FAQ
Before you renovate in The Springs and The Meadows.
Villa renovation FAQ — The Springs & The Meadows, Dubai.
01Can I extend my villa in The Springs?
Yes, on application. Emaar approves extensions case by case, townhouses included, usually with a cap on the added area relative to the existing built-up area and other conditions. We draw the extension and put it to Emaar before it is priced.
02Do I need Emaar approval for a carport or pergola in The Springs?
Yes. ECM’s Emirates Living FAQ states that any alteration to the villa has to be approved by Emaar, and it names carports, garden pergolas and pool renovations specifically.
03What can I do in a Springs villa without an NOC?
Only internal painting, furniture, electrical fixtures and regular maintenance. Anything that touches walls, services or the exterior needs an Emaar NOC first, and most alterations also need a DDA permit.
04Is the approval route the same in The Springs and The Meadows?
Yes. Both sit in Emaar’s Emirates Living master community and share the portal, the rulebook and the route: Emaar NOC first, then the DDA design and permit, then a completion inspection.
05What is the difference between Springs Type 3E and 3M?
Both are three-bedroom townhouses, but E is an end unit with one attached neighbour and a larger plot, while M is a middle unit with neighbours on both sides. That changes the plot, the party walls and the renovation that fits.
06How much does a villa renovation cost in The Springs or The Meadows?
It is a line-by-line quote against drawings rather than a flat rate. A Springs townhouse and a Meadows villa sit at different points in the per-sqft band; services, the kitchen and the ground-floor replan drive the figure most.
07How long does a Springs or Meadows renovation take?
Around twelve months from brief to handover for a full villa, with the Emaar and DDA approvals running inside the design stage rather than adding to the end.
Sources
Sources, and when we last checked them.
Every rule, fee and time on this page is as published by the body named, on the date shown. Rules and fees change, so we confirm each one at application.
All 15 sources, with links Close the detail
Official sources
- Emaar, Home Modifications Dubai factsheet, 2022.
- Emaar, Home Modifications fact sheet, 12 April 2021 (no longer online; the address now redirects to Emaar's home page).
- Emaar Community Management, Home modifications FAQ, Emirates Living.
- Emaar Master Community Rules, villas, Emirates Living, uploaded January 2026.
- Emaar Community Management, The Springs.
- Emaar Community Management, The Meadows.
- Emaar Community Management, Everything Digital, Emirates Living.
- ECM Contractors Portal, contractor registration and entry permits (ecmpermits.ae).
- Dubai Development Authority, Building Modification: Design.
- Dubai Development Authority, Building Modification: Permit.
- Dubai Development Authority, Building Modification: Completion.
Villa-type references: property portals and press
Villa renovation · The Springs & The Meadows
Start your Springs or Meadows villa in the right order.
Tell us the community, the villa type and what you want changed. We’ll come back with a scope, the Emaar and DDA route for your plot, a straight number, and a date for the site survey. Villa budgets start from AED 420.
Villa renovation specialists in Dubai · Design and build under one contract · Approvals handled with the community